Work is Slow but there is hope
Posted October 25, 2021
Work continues to be slow, but there is hope in the future:
The delivery date for furniture at The Wynn continues to change. Furniture will no longer be in at the end of October, it is looking more like December or even January pushing the Wynn remodel, that will employ 300 members, at least another month away.